Page 1 of 2
ID Task Name Duration Start Finish
1 PDOP Community Center 639 days Fri 9/11/20 Wed 3/8/23
2 Preconstruction 413 days Fri 9/11/20 Thu 4/21/22
3 Drawing Development/Preconstruction 272 days Fri 9/11/20 Mon 10/4/21
4 Issue DD Drawings 1 day Fri 9/11/20 Fri 9/11/20
5 DD Budget 15 days Mon 9/14/20 Fri 10/2/20
6 Review & Approve DD Budget 10 days Mon 10/5/20 Fri 10/16/20
7 Prepare 90% CD Documents 40 days Mon 10/19/20 Mon 12/14/20
8 90% CD Budget 15 days Tue 12/15/20 Wed 1/6/21
10 Review & Comment on 90% CD Documents 10 days Tue 12/15/20 Tue 12/29/20
11 Prepare CD Documents 85 days Wed 12/30/20 Wed 4/28/21
9 Review & Approve 90% CD Budget 10 days Thu 1/7/21 Wed 1/20/21
12 Review & Comment on CD Drawings 10 days Thu 4/29/21 Wed 5/12/21
13 Incorporate Net Zero & Develop Issued for Bid Docum5 mons ents Thu 5/13/21 Fri 10/1/21
14 Submit For Permit 0 days Mon 10/4/21 Mon 10/4/21
15 PDOP Board Review & Approvals 111 days Mon 7/12/21 Thu 12/16/21
16 Approval to Submit Net Zero Grant 0 days Mon 7/12/21 Mon 7/12/21
17 Net Zero Grant Application Process 3 mons Mon 7/12/21 Mon 10/4/21
18 Board Approval to Proceed with Bidding & Permit
Submission
0 days Thu 10/21/21 Thu 10/21/21
19 Award Recommendation Review 5 days Tue 12/7/21 Mon 12/13/21
20 Board Approval to Proceed with Awards 0 days Thu 12/16/21 Thu 12/16/21
21 Community Outreach 100 days Thu 10/21/21 Fri 3/11/22
22 Project Information Sessions for Bid Opportunities 10 days Thu 10/21/21 Wed 11/3/21
23 Project Bid Notification to MWBE Agencies 10 days Thu 10/21/21 Wed 11/3/21
24 Public Notice for Bidding 15 days Thu 10/21/21 Wed 11/10/21
25 Local Employment Outreach / Subcontractor Partnerin10 days g Mon 2/28/22 Fri 3/11/22
26 Permitting/Procurement 201 days Mon 7/12/21 Thu 4/21/22
27 Permitting 108 days Mon 7/12/21 Fri 12/10/21
28 MWRD Permit Review - 90% CDs 90 days Mon 7/12/21 Mon 11/15/21
29 Village Permit Review 30 days Tue 10/5/21 Mon 11/15/21
30 Permit Review Responses 8 days Tue 11/16/21 Fri 11/26/21
31 Final Permit Review 10 days Mon 11/29/21 Fri 12/10/21
32 Building Permit Issued 0 days Fri 12/10/21 Fri 12/10/21
33 Critical Procurement 127 days Mon 10/25/21 Thu 4/21/22
34 Subcontractor Bidding/Award Period 20 days Mon 10/25/21 Fri 11/19/21
35 Bid Leveling / Scope Review / Award Recommendations 10 days Mon 11/22/21 Mon 12/6/21
36 Underground Submittals/Approvals/Lead Time 30 days Thu 12/16/21 Thu 1/27/22
37 Concrete Submittals/Approvals/Lead Time 40 days Thu 12/16/21 Thu 2/10/22
38 Structural Steel Submittals/Approvals/Lead Time 80 days Thu 12/16/21 Thu 4/7/22
39 MEP Equipment Submittals/Approvals/Lead Time 80 days Thu 12/16/21 Thu 4/7/22
40 Glass & Glazing Submittals/Approvals/Lead Time 80 days Thu 12/16/21 Thu 4/7/22
41 Elevators Submittals/Approvals/Lead Time 90 days Thu 12/16/21 Thu 4/21/22
42 Masonry Submittals/Approvals/Lead Time 60 days Thu 12/16/21 Thu 3/10/22
43 Metal Panel Submittals/Approvals/Lead Time 60 days Thu 12/16/21 Thu 3/10/22
44 Construction 255 days Mon 3/14/22 Wed 3/8/23
45 Mobilize 5 days Mon 3/14/22 Fri 3/18/22
46 Earth Work and Foundations 51 days Mon 3/21/22 Tue 5/31/22
47 Erosion Control & Site Fencing 3 days Mon 3/21/22 Wed 3/23/22
48 Site Demo 5 days Thu 3/24/22 Wed 3/30/22
49 Surveying/Layout 3 days Thu 3/31/22 Mon 4/4/22
PDOP Community Center PDOP Community Center
Preconstruction Preconstruction
Drawing Development/Preconstruction Drawing Development/Preconstruction
Issue DD Drawings 9/11
DD Budget 10/2
Review & Approve DD Budget 10/16
Prepare 90% CD Documents 12/14
90% CD Budget 1/6
Review & Comment on 90% CD Documents 12/29
Prepare CD Documents 4/28
Review & Approve 90% CD Budget 1/20
Review & Comment on CD Drawings 5/12
Incorporate Net Zero & Develop Issued for Bid Documents 10/1
Submit For Permit 10/4
PDOP Board Review & Approvals PDOP Board Review & Approvals
Approval to Submit Net Zero Grant 7/12
Net Zero Grant Application Process 10/4
Board Approval to Proceed with Bidding & Permit Submission 10/21
Award Recommendation Review 12/13
Board Approval to Proceed with Awards 12/16
Community Outreach Community Outreach
Project Information Sessions for Bid Opportunities 11/3
Project Bid Notification to MWBE Agencies 11/3
Public Notice for Bidding 11/10
Local Employment Outreach / Subcontractor Partnering 3/11
Permitting/Procurement Permitting/Procurement
Permitting Permitting
MWRD Permit Review - 90% CDs 11/15
Village Permit Review 11/15
Permit Review Responses 11/26
Final Permit Review 12/10
Building Permit Issued 12/10
Critical Procurement Critical Procurement
Subcontractor Bidding/Award Period 11/19
Bid Leveling / Scope Review / Award Recommendations 12/6
Underground Submittals/Approvals/Lead Time 1/27
Concrete Submittals/Approvals/Lead Time 2/10
Structural Steel Submittals/Approvals/Lead Time 4/7
MEP Equipment Submittals/Approvals/Lead Time 4/7
Glass & Glazing Submittals/Approvals/Lead Time 4/7
Elevators Submittals/Approvals/Lead Time 4/21
Masonry Submittals/Approvals/Lead Time 3/10
Metal Panel Submittals/Approvals/Lead Time 3/10
Construction Construction
Mobilize 3/18
Earth Work and Foundations Earth Work and Foundations
Erosion Control & Site Fencing 3/23
Site Demo 3/30
Surveying/Layout 4/4
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter
Task Split Milestone Summary Project Summary
OAK PARK COMMUNITY CENTER
Page 1
Project: Oak Park CRC
Date: Mon 3/15/21
Page 2 of 2
ID Task Name Duration Start Finish
50 Excavate for Foundations 10 days Tue 4/5/22 Mon 4/18/22
51 Pour Footings/Foundation Walls/GBs 20 days Tue 4/12/22 Mon 5/9/22
52 MEP Underground MEP Rough 10 days Tue 5/10/22 Mon 5/23/22
53 Backfill Foundations/Stone SOG Area 5 days Tue 5/24/22 Tue 5/31/22
87 Site Improvements 144 days Tue 5/10/22 Wed 11/30/22
88 Site Utilities / Street Connections 15 days Tue 5/10/22 Tue 5/31/22
89 Final Grading 5 days Thu 10/20/22 Wed 10/26/22
90 Site Concrete 10 days Thu 10/27/22 Wed 11/9/22
91 Pavers 15 days Thu 11/10/22 Wed 11/30/22
92 Landscaping 5 days Thu 11/10/22 Wed 11/16/22
54 Superstructure 54 days Wed 6/1/22 Tue 8/16/22
55 Erect Structural Steel 25 days Wed 6/1/22 Wed 7/6/22
56 Detail Steel 15 days Wed 6/22/22 Wed 7/13/22
57 Install Metal Deck/Shear Studs 10 days Thu 7/7/22 Wed 7/20/22
58 Pour Concrete 2nd Floor & SOG 8 days Thu 7/21/22 Mon 8/1/22
59 Pour Concrete Mezzanine & Roof 6 days Tue 8/2/22 Tue 8/9/22
60 Steel/Concrete Weather Days 5 days Wed 8/10/22 Tue 8/16/22
61 Structure Complete 0 days Tue 8/16/22 Tue 8/16/22
62 Façade and Envelope 87 days Wed 8/17/22 Fri 12/16/22
63 Exterior Framing 25 days Wed 8/17/22 Wed 9/21/22
64 Exterior Masonry/Elevator Shaft 25 days Thu 9/22/22 Wed 10/26/22
65 Metal Panels 35 days Thu 9/22/22 Wed 11/9/22
67 Roof Vapor Barrier - Water Tight 10 days Thu 10/27/22 Wed 11/9/22
66 Glazing 25 days Mon 10/31/22 Fri 12/2/22
68 Roof 15 days Thu 11/10/22 Wed 11/30/22
69 Roof Coping 10 days Mon 12/5/22 Fri 12/16/22
70 MEP 105 days Wed 8/17/22 Wed 1/11/23
71 Level 1 MEP Rough 15 days Wed 8/17/22 Wed 9/7/22
72 Level 2 MEP Rough 15 days Thu 9/8/22 Wed 9/28/22
73 Gym MEP Rough 15 days Thu 9/29/22 Wed 10/19/22
74 Set Rooftop Equipment 5 days Thu 12/1/22 Wed 12/7/22
75 Vertical Transportation 30 days Thu 12/1/22 Wed 1/11/23
76 Interiors 125 days Wed 8/17/22 Wed 2/8/23
77 Erect Stairs 15 days Wed 8/17/22 Wed 9/7/22
78 Frame Partitions 20 days Thu 9/8/22 Wed 10/5/22
79 Drywall / Tape / Paint 30 days Thu 11/10/22 Wed 12/21/22
84 Install Overhead Equipment 15 days Thu 12/15/22 Wed 1/4/23
80 Floor Finishes 20 days Thu 12/22/22 Wed 1/18/23
81 Fixture Trim Out 15 days Thu 12/22/22 Wed 1/11/23
82 Install Track Flooring 15 days Thu 12/22/22 Wed 1/11/23
83 Install Gym Flooring 20 days Thu 1/5/23 Wed 2/1/23
85 Final Clean 5 days Thu 2/2/23 Wed 2/8/23
86 Final Inspections 5 days Thu 2/2/23 Wed 2/8/23
93 Closeout/Transition 20 days Thu 2/9/23 Wed 3/8/23
94 Punchlist/Commissioning 10 days Thu 2/9/23 Wed 2/22/23
95 Final Occupancy 0 days Wed 2/22/23 Wed 2/22/23
96 Owner Move In 10 days Thu 2/23/23 Wed 3/8/23
97 Project Complete 0 days Wed 3/8/23 Wed 3/8/23
Excavate for Foundations 4/18
Pour Footings/Foundation Walls/GBs 5/9
MEP Underground MEP Rough 5/23
Backfill Foundations/Stone SOG Area 5/31
Site Improvements Site Improvements
Site Utilities / Street Connections 5/31
Final Grading 10/26
Site Concrete 11/9
Pavers 11/30
Landscaping 11/16
Superstructure Superstructure
Erect Structural Steel 7/6
Detail Steel 7/13
Install Metal Deck/Shear Studs 7/20
Pour Concrete 2nd Floor & SOG 8/1
Pour Concrete Mezzanine & Roof 8/9
Steel/Concrete Weather Days 8/16
Structure Complete 8/16
Façade and Envelope Façade and Envelope
Exterior Framing 9/21
Exterior Masonry/Elevator Shaft 10/26
Metal Panels 11/9
Roof Vapor Barrier - Water Tight 11/9
Glazing 12/2
Roof 11/30
Roof Coping 12/16
MEP MEP
Level 1 MEP Rough 9/7
Level 2 MEP Rough 9/28
Gym MEP Rough 10/19
Set Rooftop Equipment 12/7
Vertical Transportation 1/11
Interiors Interiors
Erect Stairs 9/7
Frame Partitions 10/5
Drywall / Tape / Paint 12/21
Install Overhead Equipment 1/4
Floor Finishes 1/18
Fixture Trim Out 1/11
Install Track Flooring 1/11
Install Gym Flooring 2/1
Final Clean 2/8
Final Inspections 2/8
Closeout/Transition Closeout/Transition
Punchlist/Commissioning 2/22
Final Occupancy 2/22
Owner Move In 3/8
Project Complete 3/8
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter
Task Split Milestone Summary Project Summary
OAK PARK COMMUNITY CENTER
Page 2
Project: Oak Park CRC
Date: Mon 3/15/21